Vinay can do a certain work in 16 days. Shubham is 60% more efficient than Vinay. How many days does Shubham............

0 votes
130 views

Vinay can do a certain work in 16 days.
Shubham is 60% more efficient than Vinay.
How many days does Shubham alone take to do the same work?

posted Jan 8, 2021 by Pushpak Chauhan

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

2 Answers

0 votes

work done by Shubham 1/10
no of days need to complete work by him 10

answer Jan 9, 2021 by Gangadharan Kv
0 votes

work done shubham 1/10
hence answer 10days

answer Jan 14, 2021 by anonymous



Similar Puzzles
0 votes

B is more efficient than A and they together can complete a work in 18 days.
Had A done 60% of the work and then B, the remaining work, then the work would have been completed in 39 days.
B alone will complete 60% of the same work in how many days?

0 votes

C with his 200% efficiency, can complete 25% of a certain work in 12 days.
B is 20% more efficient than C.
A with 75% efficiency can complete the work in same days as B.
If A and B together finish the same work and A gets Rs. 10400, then what is the share of B?

0 votes

B alone can complete the work in 45 days.
A is 35% more efficient than B.
If A and B together started the work but after 18 days A and B left.
Then C alone completed the remaining work in 3 days.
If they get Rs. 9750 as wages for the whole work, then what is the share of C in wages for the remaining work?

0 votes

A alone can complete a piece of work in 30 days.
B is 50% more efficient than A.
With the help of C, together they completes the work in 6 days, then C is ____ efficient than ______.
Fill in the blanks.

...