top button
Flag Notify
    Connect to us
      Facebook Login
      Site Registration Why to Join

    Get Free Puzzle Updates

Facebook Login
Site Registration

40 men can build a wall 20m high in 15 days. How many men required to build a similar wall 50 m high in 3 days?

+1 vote
898 views
40 men can build a wall 20m high in 15 days. How many men required to build a similar wall 50 m high in 3 days?
posted Oct 6, 2016 by anonymous

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

5 Answers

+1 vote
 
Best answer

40 men can build 20m high wall in 15 days
=> 1 men can build 20m high wall in 15*40 days
=> 1 men can build 1m high wall in 15*40/20 i.e. 30 days
=> 30 days 1m high wall requires 1 men
=> 30 days 50m high wall requires 1*50 men
=> 3 days 50m high wall required 1*50*10 men

Answer:
500 Men required

answer Oct 7, 2016 by Salil Agrawal
exactly correct answer 500men require to build 50 m hight wall in 3 days
+1 vote

500 men is the correct answer.

The answer can be arrived at by increasing the number of men according to the following ratios:
40 men*(50m/20m)*(15days/3days) = 40men*2.5*5 = 500men

answer Oct 8, 2016 by George Davros
0 votes

20 men is the answer:

First convert into meters per day/man: 20*15 = 300 meters per day/40 men = 7.5 meters per day/man
Then answer the question by using the new parameters: (50 meters)(3 days) = 150 meters per day/7.5 meters per day/man = meters per day canceling out leaving: 20 men are the new requirement.

Correction:

500 men is the correct answer.

The answer can be arrived at by increasing the number of men according to the following ratios:
40 men*(50m/20m)*(15days/3days) = 40men*2.5*5 = 500men

BTW: a thank you to those that provided the correct answer. Learning from mistakes allows a person to try different solutions.
And by being provided with the correct answer you can work the problem backwards, similar to reverse engineering.

answer Oct 6, 2016 by George Davros
0 votes

500 members required

answer Oct 7, 2016 by Jaganathan
0 votes

1.- 40 men build a wall 20 mts high in 15 days
2.- 40 men will build a wall 50 mts high in 15 x 50/20 ( 37,5 days)
3.- X men will build a wall 50 mts high in 37,5 / 12,5 ( 3 days)
Then the number of men will be : 40 x 12,5 = 500 men
The answer is 500 men

answer Oct 19, 2016 by anonymous



Similar Puzzles
0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

+1 vote

If 15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

0 votes

Rahul forms a wall in 10 days and Sahil forms a wall in 15 days. Rahul and Sahil start the work of forming wall together but after 2 days Rahul leaves the work.
How many days are required for making the remaining wall by Sahil?

0 votes

A certain number of men can finish a piece of work in 30 days.
If however there were 15 men less it will take 30 days more for the work to be finished.
How many men were there originally?

Contact Us
+91 9880187415
sales@queryhome.net
support@queryhome.net
#280, 3rd floor, 5th Main
6th Sector, HSR Layout
Bangalore-560102
Karnataka INDIA.
QUERY HOME
...