A certain number of men can finish a piece of work in 30 days. If however............How many men were there originally?

0 votes
262 views

A certain number of men can finish a piece of work in 30 days.
If however there were 15 men less it will take 30 days more for the work to be finished.
How many men were there originally?

posted Mar 12, 2019 by Atif

Share this puzzle
Facebook Share Button Twitter Share Button LinkedIn Share Button

1 Answer

0 votes

Speed reduced to half by 15 people implies 15 people make half of the work group, making the total strength = 30

N men can do 1 work in 30 days
(N - 15) men can do 1 work in 60 days
Speed of N men = 1 work / 30 days
Speed of (N - 15) = 1 work / 60 days
Speed of 1 man = 1 work / (30×N days) = 1 work / (60×(N - 15) days)
30N = 60N - 900
30N = 900
N = 30 men.

answer Mar 12, 2019 by Tejas Naik



Similar Puzzles
0 votes

A certain number of workers can finish a piece of work in 100 days.
If there were 10 workers less, it would take 10 days more for the work to be finished.
How many workers were there originally?

0 votes

8 woman and 12 men complete a certain piece of work in 9 days. Each woman takes twice the time taken by a man to finish the work. In how many days will 12 men finish the same work

0 votes

Six men do a piece of work in 10 days with an effort of 6 hours per day. How many extra men are required for doing the work of double strength in 4 days with an effort of 5 hours per day

0 votes

A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

...